Relativity Space is assembling and testing Terran R, a large orbital rocket designed to carry satellites and recover its first stage for another flight. The Long Beach, California, company has concentrated its launch business on this vehicle after retiring Terran 1, the smaller rocket that flew once in March 2023. Its current program combines engine production, full-stage testing in Mississippi, and construction at Cape Canaveral’s Launch Complex 16.
Under chief executive Eric Schmidt, Relativity has also expanded into spacecraft development through a planned Mars science mission. Its company profile describes an organization of approximately 2,000 employees, with operations in California, Mississippi, Florida, Washington state, and Washington, D.C. Launch manufacturing remains centered in Long Beach, where propulsion, structures, and vehicle integration are brought together within the company’s own production facilities.
Terran 1 and the Transition to a Larger Rocket
Terran 1 established Relativity’s original approach to rocket production through extensive metal additive manufacturing, commonly called 3D printing. Instead of starting every structure with large pieces of material that are machined down, additive processes build components by depositing or fusing material in successive layers. Approximately 85% of the first rocket was produced with 3D printing. The flight vehicle stood about 110 feet tall and used two stages to divide the work of accelerating toward orbit.
The rocket lifted off from Cape Canaveral at 11:25 p.m. Eastern time on March 22, 2023. During the ascent, it passed through the period of maximum aerodynamic loading, when the combined effects of speed and air density impose substantial forces on the vehicle. The first stage completed its burn and separated. However, the second-stage engine failed to develop the thrust needed to continue the mission, and Terran 1 did not reach orbit.
Relativity now identifies Terran 1 as a retired pathfinder. The company attributes experience in methane and liquid-oxygen propulsion, gas-generator engines, flight software, guidance, structural behavior, and aerodynamic heating to that program. These are connected elements of a launch system: the engines provide force, the structures carry the loads, and the control system continually adjusts the trajectory. Terran 1 supplied flight data on their interaction during the first-stage portion of an orbital launch attempt.
The shift to Terran R was formalized in an April 2023 program announcement. Relativity selected a much larger vehicle with first-stage recovery and sufficient payload capacity to launch groups of constellation satellites or individual large spacecraft. The announced payload-integration approach accommodated dedicated missions and rideshare configurations. Customers could place their spacecraft on a standard attachment interface, with integration performed while the rocket was horizontal.
Terran R Architecture and Payload Capacity
The current Terran R design is 86.6 meters tall, with a 5.4-meter vehicle diameter and payload fairing. Aluminum alloys form its structure. The fairing encloses the spacecraft during ascent through the atmosphere, protecting them from aerodynamic loading and the external environment. Its dimensions determine the available envelope for satellites and their deployment hardware, alongside the rocket’s separate limits on payload mass.
Relativity advertises a capacity of 23,500 kilograms to low Earth orbit with downrange recovery of the first stage, or 33,500 kilograms when the vehicle is expended. For geosynchronous transfer orbit, the stated capacity is 5,500 kilograms with downrange recovery. These are design performance figures for the development vehicle. The company vehicle page reviewed in November 2026 continued to identify late 2026 as its planned launch starting period.
Downrange recovery places the landing platform farther along the flight path, out over the ocean. The booster separates from the upper stage, adjusts its orientation, descends through the atmosphere, and uses engines for the landing. Relativity’s announced recovery sequence includes aerodynamic control with grid fins and landing legs that deploy before touchdown. Inspection and refurbishment in Florida are intended to prepare recovered boosters for subsequent missions.
The recovery and expendable performance figures describe two different uses of the same launch architecture. A recovery mission reserves propellant and carries the hardware used during descent and landing. An expendable mission can devote more of the vehicle’s available performance to delivering the payload. Terran R’s advertised difference is 10,000 kilograms to low Earth orbit, giving its intended customers a choice between payload mass and booster recovery within the offered service.
Low Earth orbit missions and geosynchronous transfer missions also impose different energy demands. A transfer orbit sends a spacecraft onto an elongated path with a high point far above Earth; the spacecraft can then use its own propulsion to reach its operating orbit. This helps explain why Terran R’s published transfer-orbit payload is smaller than its low Earth orbit payload. The distinction is directly relevant to Relativity’s contracts with communications satellite operators serving more than one orbital region.
Aeon Engines and Full-Stage Testing
Terran R uses 13 Aeon R engines on the first stage and one Aeon V engine on the upper stage. Both burn methane with liquid oxygen and use a high-pressure gas-generator cycle. In this arrangement, a portion of the propellants supplies hot gas to drive the machinery that pumps the main propellant flow. Relativity lists 269,000 pounds-force of sea-level thrust for each Aeon R and 323,000 pounds-force in vacuum for Aeon V.
The vacuum engine operates after the vehicle has climbed beyond the dense lower atmosphere. Its nozzle is adapted to that environment, allowing the exhaust to expand farther than a comparable sea-level nozzle. Relativity’s September 2025 development update reported a 475-second mission-duration Aeon V test with densified liquid oxygen. Testing an engine through a representative burn duration measures its behavior over the sustained operating period required of an upper stage.
Engine acceptance testing checks the individual hardware intended for flight after the engine design has been developed and qualified. Relativity reported completion of Aeon V acceptance testing in its July 2026 update, concluding engine testing for the first vehicle. The same update documented completion of the first-stage structural qualification campaign, including 420 pressure cycles and 62 loading cases. The dedicated structural article experienced axial compression of 4.3 million pounds-force under pressure.
The upper stage also completed cryogenic proof testing at NASA’s Stennis Space Center. This exposed its tanks and associated systems to pressure with very cold fluids, extending earlier testing performed with water. Pressure vessels that support the propellant-pressurization system underwent their own proof tests. These activities addressed the assembled stage and its fluid systems, complementing tests of the engine as a separate unit.
By the August 2026 production update, all 13 first-flight booster engines had been installed on the thrust structure. Manufacturing was also proceeding on subsequent vehicles: the second vehicle’s barrel sections had completed circumferential friction-stir welding, and panel production was progressing for the third. Friction-stir welding joins material through a rotating tool that generates heat and mechanically mixes the joint, forming the seams between tank sections.
Integration continued with installation of the first-stage downcomer, the internal feedline that carries oxygen toward the engines. Relativity’s September update also described engine movement checks, ground-station work, and upper-stage preparations at the A2 test stand. On October 16, the company reported the upper stage’s first integrated hot-fire test, a milestone subsequently covered in October reporting on launch development. That test brought the stage’s propulsion and supporting systems together during an engine firing.
Relativity’s industrial facilities divide the program geographically. The Long Beach headquarters, called the Wormhole, provides approximately one million square feet for production. Its manufacturing methods include powder-bed additive manufacturing and computer-controlled machining. A separate facility known as the Portal supports research and development involving Stargate metal-printing technology. The present manufacturing organization combines these processes with the fabrication and joining methods used for the large vehicle structures.
Manufacturing, Testing, and Launch Operations
In Mississippi, Relativity operates engine and stage-test infrastructure at Stennis. Its facilities include the R complex for engine testing and the A2 stand for stage tests. The distinction follows the hardware being evaluated: engine stands support propulsion development and acceptance, and the larger stage stand accommodates tanks, plumbing, control equipment, and an installed engine together. Florida hosts the launch end of this production and test sequence at Launch Complex 16.
Moving large stages between these sites is itself part of the production process. In its June 2026 update, Relativity described the upper stage’s sea journey through the Panama Canal to Gulfport, Mississippi, followed by a barge transfer toward Stennis. The company also installed a large flame diverter at A2. This structure directs the engine’s exhaust away from the stage and test-stand equipment during firings.
Launch-site work has included the horizontal integration facility, transporter-erector hardware, electrical infrastructure, and propellant-support equipment. The integration building provides a controlled location for assembling the stages before the rocket is moved to the pad and raised vertically. Relativity’s July report described activation of permanent power and a proof-load test for the assembly-room crane. These installations support the physical sequence from delivered hardware to an integrated launch vehicle.
Commercial Missions and Government Contracts
Relativity’s commercial model is to sell launch services using its own rocket, production system, test facilities, and launch site. Its position among American commercial launch providers reflects the move from a small satellite launcher toward a vehicle able to carry large batches of spacecraft. The company reports more than $3 billion in launch-service agreements across commercial, telecommunications, and government customers and partners.
Communications operator SES is one publicly identified customer. On November 12, 2025, the companies announced an expanded multilaunch agreement covering selected satellites for geostationary or medium Earth orbit. The arrangement extends over multiple years and includes previously unannounced launches. It links Terran R to SES’s use of satellites in different orbital regions, rather than restricting the rocket’s commercial role to low-orbit constellations.
NASA added Terran R to its Launch Services II contract in September 2026. The contract provides a framework under which the agency can acquire launch services for future missions. Its ordering period runs through June 2030, with mission performance extending through December 2032. Relativity’s addition places Terran R within that procurement framework as the company develops the vehicle and its associated launch service.
The NASA arrangement is a multiple-award, indefinite-delivery/indefinite-quantity contract. Its annual on-ramp allows new providers to join and existing providers to offer additional vehicles. Managed by the Launch Services Program at Kennedy Space Center, it supports science, human spaceflight, and technology missions. NASA can also use the framework to provide launches for other federal agencies, including the National Oceanic and Atmospheric Administration.
A Planned Mars Science Mission
Relativity’s spacecraft activities provide another intended application for its launch capability. In June 2026, NASA announced a Mars science partnership in which Relativity supplies the spacecraft, rocket, and cruise operations. NASA supplies Aeolus, a suite of four atmospheric-science instruments scheduled for launch in 2028. Researchers at Ames Research Center are responsible for designing, building, and integrating that payload.
The instruments are intended to measure Martian winds, temperatures, dust, and clouds, with complementary observations providing a daily global picture of atmospheric conditions. Relativity is responsible for spacecraft development and mission operations, and NASA will operate the science instruments for at least one Martian year. The planned mission extends the company’s work from carrying customers’ satellites to providing both the transportation and spacecraft supporting a scientific investigation at Mars.
Relativity also plans to equip the Mars orbiter with a shallow radar sounder to investigate subsurface ice and geology. Its Interplanetary Sciences Program describes a proposed onboard data center with computing, storage, and communications equipment. The spacecraft is intended to provide optical and radio-frequency links with Earth, together with radio relay connections to surface missions. This combines scientific measurements and data transport within the company’s announced 2028 spacecraft mission.