Utah’s Spaceport Exploration Committee recommended US$2.5 million to advance Delta and Green River West through licensing and environmental review, in a final report heard by state lawmakers on November 18, 2026. The proposal would fund the next phase of work on two potential locations for a land-based spaceport.
The final report, dated October 30, recommends that the Utah Department of Transportation lead the work. Its funding request covers licensing and related technical analysis for both locations. Land acquisition and physical development are outside that US$2.5 million allocation.
The report also recommends at least two dedicated full-time positions within the transportation department, at an estimated annual cost of US$500,000. Those staff would support licensing, planning, and coordination as the proposal moves beyond initial site screening.
The legislature created the exploration committee in 2025 through Senate Bill 62. An initial review considered seven candidate sites, and Delta and Green River advanced as finalists in June 2026. The final report identifies Delta and Green River West as potential locations and proposes retaining both in the next stage.
Earlier coverage of Utah’s draft study described a phased development approach that favored starting at Delta and retaining Green River West for potential later activity. The final committee recommendations now put both sites forward for coordinated federal licensing and environmental work.
A spaceport operator license concerns the location and its approved operating arrangements. Launches and reentries conducted there also require the applicable authorizations for the vehicles and activities involved. The report proposes pursuing launch-site and reentry-site licensing processes with the Federal Aviation Administration.
Environmental review would accompany that work under the National Environmental Policy Act. The committee proposes that the licensing allocation support technical studies and public involvement. Both locations remain proposed facilities, subject to the required federal reviews and subsequent development decisions.
The transportation department’s recommended responsibilities extend beyond preparing an application. The report assigns it a prospective role in site planning, financing analysis, procurement, land acquisition, partnerships, design, construction, and commissioning. Progress into development would follow favorable federal reviews.
The committee also recommends securing control of land to preserve the state’s development options. Site control is part of preparing a location for a defined use, separate from committing funds to construct the full facility. The final recommendations distinguish land arrangements, licensing expenditure, and later development activity.
The November 18 hearing agenda placed the report before the Economic Development and Workforce Services Interim Committee, with the transportation department presenting it. This brought the exploration committee’s recommendations into the legislature’s interim review process.
The report recommends extending the exploration committee for three years in an advisory role through the expected licensing and environmental-review period. Under that proposal, the transportation department would lead the work and the committee would advise on it.